Discharging of 3 casco's from a transport vessel

Market: Heavy Lift

Scope of Work: Discharging of 3 casco's from transport vessel ALL Antwerp

Location: Rotterdam, The Netherlands

Client: Bonn & Mees Drijvende Bokken BV

Periode: August 2025

HLV: Gulliver

Scaldis was contacted by Bonn & Mees to provide heavy lift assistance for the discharging of 3 casco’s from transport vessel AAL Antwerp:

  • 1x tandem lift with Gulliver, Matador 3 and Hebo Lift 7
  • 2x tandem lift with Gulliver and Matador 3

Casco 1: 1091 tonnes

Casco 2: 1437 tonnes

Casco 3: 1444 tonnes

Prepare Heavy Lift Vessel Gulliver for departure

Mobilise HLV Gulliver to the work site in Rotterdam, The Netherlands

HLV to drop bow anchors & position at transport vessel

Connect rigging to the casco (#01 #02 #03)

Lift the casco (#01 #02 #03) off the transport vessel

HLV reposition to discharge location

Launch (#01 #02 #03) into the water

Disconnect rigging & retrieve anchors

Demobilisation and clearance Heavy Lift Vessel Gulliver