Market: Heavy Lift
Scope of Work: Discharging of 3 casco's from transport vessel ALL Antwerp
Location: Rotterdam, The Netherlands
Client: Bonn & Mees Drijvende Bokken BV
Periode: August 2025
HLV: Gulliver
Scaldis was contacted by Bonn & Mees to provide heavy lift assistance for the discharging of 3 casco’s from transport vessel AAL Antwerp:
- 1x tandem lift with Gulliver, Matador 3 and Hebo Lift 7
- 2x tandem lift with Gulliver and Matador 3
Casco 1: 1091 tonnes
Casco 2: 1437 tonnes
Casco 3: 1444 tonnes
Prepare Heavy Lift Vessel Gulliver for departure
Mobilise HLV Gulliver to the work site in Rotterdam, The Netherlands
HLV to drop bow anchors & position at transport vessel
Connect rigging to the casco (#01 #02 #03)
Lift the casco (#01 #02 #03) off the transport vessel
HLV reposition to discharge location
Launch (#01 #02 #03) into the water
Disconnect rigging & retrieve anchors
Demobilisation and clearance Heavy Lift Vessel Gulliver